Confederation Line - Stage 1 - Construction Updates

Recommended Posts

This week's construction update has two very exciting photos contained within. (Both photos credit to City of Ottawa : https://www.ligneconfederationline.ca/news/construction-update-195/)

The first is a picture of the main concourse of Lyon Station. Big and vast are two words that spring to mind.

Work-is-ongoing-at-Lyon-Station-2018-09-25-1024x768.thumb.jpeg.c01bc646d24f12a8a4968d7bd2c046b0.jpeg

The second is of St. Laurent Station where you can see two trains coupled together.

LRV-testing-at-St.-Laurent-2018-10-09-2-1024x768.thumb.jpg.d06de35f6af8180279b13682888c734c.jpg

Just these two pictures draw a lot of excitement, as you can see in big ways that the work in most stations is quickly coming to an end. Granted Rideau Station is still the spot with the most work remaining, the rest of the network is wrapping up.

According to the Construction Update this week, the section from Blair to Hurdman is pretty much done, with just minor work and finishing occurring, in tandem with testing and commissioning operations.

It's been a busy month and a half for me but I will be getting back out there to resume posting Snapshot updates in a week's time.

Share this post


Link to post

Good Day.

Re: Lyon pic.....

to my eye, not so much. Of course, pics do not really show in person live actual perceived space (and I am from Montreal, so I am biased !)....

and this is the concourse level, after the fare gates and before you descend to platform level, so people will not spend too much time here.

Of more concern is the platform level....which, from pics so far (and Parliament station just about the same), show (to me) very cramped platforms.

We shall see ......

Share this post


Link to post

I was passing through Place de Ville earlier this week and noticed that the construction hoardings that had been up for several years have finally been removed.

It is now possible to see the interior integrated entrance to Lyon Station.

I had shared it on Twitter and there were a few comments about why there was any need for doors. Several reasons could include air flow (anyone who has been to Montreal knows that the suction and vaccuum created by the train movements can be quite strong), so this would need to be controlled or the air in Place de Ville could also be affected. The doors create a barrier and buffer to help limit this. Another reason is for fire safety, to help segregate the various areas. Access control after hours is a third.

I thought the entrance would have been a bit more elaborate or with more doors (similar to the interior entrance in the Sun Life Financial Centre at Parliament Station). Overall, the people using these doors will be people working at Place de Ville or staying at the hotels. Still, I would have preferred two sets of double doors.

IMG-0530.thumb.jpg.8329a0c05bb37f337ab1bb2e38f69274.jpg

IMG-0532.thumb.jpg.a8f4f6145301f117a12053c1cd785ee5.jpg

Share this post


Link to post

Good Day.

As for doors rather than a drop chainlink gateway.... yep - airflow control is the most probable explanation. You see doors at the lower level St. Laurent access as well.

Even though both have or should have good vent stacks, airflow is still a bear.

Indeed, as you mention (I am from Montreal originally) Montreal has some stations that are fierce. Peel - Concordia comes to mind.

Most of the rolltop gateways are at open-air stations - a far less problematic location / situation.

EnJoy!

Share this post


Link to post

Installed today, the Lyon Station signs at the Podium Building entrance. 

191DA3F2-9149-44FF-ADF6-D35F34CFBE1A.thumb.jpeg.47bc58e257c79dcca953f9d5202131fd.jpeg

Share this post


Link to post

Following up from my photos a bit higher of the interior entrance within Place de Ville to Lyon Station, this weeks construction update has a photo of inside the station, directly on the opposite side of those doors. 

You can see the doors just to the right of the escalators and stairs if you follow down the ramp on the right side of the image. 

D27D865E-793A-4A87-BAF2-ED99A6E4E726.thumb.png.bc12a569ac7cf0a706fb8307af5daa92.png

Share this post


Link to post

The November 8, 2018 Construction Update has several interesting details to report.

Quote

Construction Update

The track and Overheard Catenary System (OCS) are certified for operation at line speed (50 km/hr); some vehicles are also certified for line speed operations. End-to-end guideway testing is ongoing at full line speed. Coupled train testing continues. Landscaping works as well as testing and commissioning occur throughout the alignment. At the downtown stations, the installation and testing of fare gates is underway.

Guideway and Testing

Communications Based Train Control (CBTC) testing in the tunnel is now complete and the entire guideway is now available for Automatic Train Operation (ATO). The track and Overhead Caternary System (OCS) are certified for operation at line speed, with some vehicles in the fleet also certified for line speed operations. End-to-end guideway testing is ongoing at line speed. Coupled train testing continues.

This is all very promising news, and helps to show that things are definitely advancing. Automatic train control and the CBTC systems are key for system certification and acceptance. To read that the trains are now able to run from end to end in Automatic Train Operation is excellent news. Even more, that the track and catenary system are certified for line speed.

From the update it would seem like most of the work on the infrastructure is surrounding Tunney's Pasture (landscaping and surrounding finishes), and Parliament / Rideau Stations to a higher degree.

I'm still optimistic for a handover before the end of the year, of course we should get a better idea at the FEDCO meeting next Wednesday.

Becoming more and more optimistic.

Share this post


Link to post

I was hoping for sooner but his words do say By The End of March. So could also mean March at the latest.

I'm still hoping for earlier.

I guess we will have some big news on the date at the FEDCO on Wednesday. 50 hours to go.

Share this post


Link to post

Me too I was hoping for earlier and thanks Shane for your great work posting pictures and FEDCO reports. I have been in Ottawa too long I believe for the way I read the Mayor's reply is that we will have a date by the end of March... not that it will open by then. But I think that is too pessimistic. 

At some point they cannot be that incompetent. From the the pictures and various reports from commenters, March sounds reasonable. 

Share this post


Link to post

Thanks Shane for the FEDCO report and the video. 

They are further along than I thought reading from various reports. This is encouraging and March is certainly doable and like others see that as more of a deadline than a target. While we won’t know for sure till RTG reports, am sure the city has performed its own evaluation for Mayor Watson to tweet end of March. 

By March the system should be up and running. 

Share this post


Link to post

I have little doubt they will open by end of March, but I'm hopeful for even sooner. Lots of progress made over the past few months, it's really impressive.

I guess we can put January 2nd on calendar as the deadline to find out the new RSA date. They have 60 days from the last one of November 2nd to announce a new Revenue Service Availability date. That's a month and a half away.

I would expect we would hear something before Christmas, as after that it's just a week away and with holidays and New Year's... doubtful they would announce something in that week period, unless they want to be dramatic due to the holidays.

  • Thanks 1

Share this post


Link to post

Create an account or sign in to comment

You need to be a member in order to leave a comment

Create an account

Sign up for a new account in our community. It's easy!

Register a new account

Sign in

Already have an account? Sign in here.

Sign In Now

O-Train Fans is not affiliated, nor connected to either OC Transpo or the City of Ottawa.
Any customer related inquiries should be directed to them and not this site by visiting the OC Transpo or the City of Ottawa websites.
×